Pipeline Division Projects

Safety, Quality & Man Power

 
copy+with+eq.jpg

The pipeline division has the support & resources that Marsau has been building since 1982.

Marsau offers a large variety of services.

Marsau’s pipelines division has installed 200 to 300 miles of of pipe per year in all sizes & types of pipeline over the last decade.

The sizes of pipe range from 3" to 24". With the newest part of our pipeline division we have pipeliner’s that are exclusive to Midstream Companies.  In our steel division we have constructed more than 40 gas compressor stations from the first weld on the skid to turning on the station. We install, swap & replace compressor motors as needed.

Over the years we have worked for multiple Midstream companies. During this time we have constructed over 50 compressor stations, we have installed 300 miles of poly per year, ranging various sizes of pipe, from 4” to 24”. Since developing the pipeline division we have been averaging 115 miles of steel lines per year. Both transmission & gathering, DOT regulated systems.

Welders that are specialized is pipe fabrication, for launchers & receivers, meter piping, camel backs, above ground valve settings, compressor station piping, flow control piping, ultra-sonic meter skid piping & lact piping.  

 Hot taps on both steel & poly lines are performed by Marsau’s employees. We also perform stopples and do hydro-static pressure testing.


Great Salt Plains

GSPM-10" EAST MAIN GAS HEADER LAY 33,000' OF 10"

CWC 6" LAY 33,514' OF 6" STEEL s

10" SOUTH CHISHOLM WEST LAY 36,960' OF 10" STEEL

 GSPM-6" SOUTH CHISHOLM WEST LAY 36,960' OF 6" STEEL

CWG JASPER LAY 5,600' OF 6" STEEL

COLONEL COBB 18-08-26 1H LAY 8,000' OF 6"

LAROCHE 1H LAY 7,958' OF 6" STEEL

COMANCHE 1H LAY 6,302' OF 6" STEEL

6" CWG STAMPEDE LAY 6,879' OF 6" STEEL

4" CWG STAMPEDE LAY 6,879' OF 4" STEEL

COLONEL COBB 18-08-26 1H LAY 8,000' OF 4" STEEL

SCWG 12" STEEL - DIXON LAY 21,120' OF 12" STEEL

SANDHILLS TO GADWALL LAY 18,117' OF 12" STEEL

SCWC 6" STEEL-LONGHORN LAY 14,381' OF 6" STEEL

SCWC 6" STEEL DIXON LAY 21,120' OF 6" STEEL

CWC THAMIN LAY 39,664' OF 4" STEEL

MATILDA 19-08-25 1H 12,087' OF 4"

SALLY SCULL 19-07-19 1H 583' 4" STEEL

CATTLE DRIVE 18-09-23 1H 1,384' OF 4" & 1,718' OF 4"

BOETTLER 1 MH INSTALL 1,715' 4" STEEL

MAGGIE 4" & 6" STEEL PIPELINE 4"STEEL-1138' 6"STEEL 1138'

ROY SUGGS 4" & 6" STEEL PIPELINE 4"STEEL-3500 6"STEEL 3500

DORA TO STAMPEDE LAY -18,812' OF 6" STEEL LAY -19,082' OF 4"

Kinder Morgan

WATONGA LINE - LAY 31,800 16”STEEL

CLR BLONDIE #1 LAY 4,288' OF 6" STEEL

FORE TRIUMPH WELL CON LAY 10,800' OF 8" POLY

TRIUMPH MADDOX 1/22WC LAY 2,833' OF 6" SDR11 POLY

Superior Pipeline

SOUTH PIEDMONT GATHERING LAY 111,300’ OF 12” STEEL

BIG MUDDY / LILLIAN Active 8,000' 12" STEEL PIPELINE

DANNEHL 1405 2-34MH 7,304' of 8" STEEL

PAN HANDLE EASTERN 12,778' OF 10" STEEL

RED BLUFF CORNELL LAY 1,200' OF 6" POLY

LEON TREECE LAY 1,300' OF 8" POLY

STEPHENS EMMERICH 3-6 INSTALL 3,969' POLY

RED BLUFF CHRISTENSEN LAY 10,567' 8" POLY

RED BLUFF RUSSELL3-31 Active 16,387' OF 10" POLY

EMMERICH 2-6H LAY 7,481' OF 10" POLY